Codex principle 5 and step 10: establish corrective action

Annex A stepMapped in the current Annex A to 8.5.4, 8.9.2 and 8.9.3; the 2026 table is sold by ISO and not held hereRetrieved 2026-10-19Last updated: 2026-10-19

The requirement that applies today

The fifth Codex principle, at step 10, is to establish the corrective action to take when monitoring shows a CCP is out of control. The current edition maps it to the hazard control plan, corrections and corrective actions.

ISO/DIS 22000:2026, Annex A 9, Codex principle 5 and step 10: establish corrective action.

What the draft does

Mapped in the current Annex A to 8.5.4, 8.9.2 and 8.9.3; the 2026 table is sold by ISO and not held here: The 2026 contents keep all three clause titles. For this row the inferred 2026 destination is 8.5.4.4, 8.9.2, 8.9.3; that reading comes from the clause titles, not from the published 2026 table.

Source: public contents and foreword at A.9, retrieved 2026-10-19.

Why this clause matters

The distinction between a correction and a corrective action is the difference between fixing the batch and fixing the system. The clause requires both, and the record has to show the product decision and the cause. The 2026 contents keep all three destinations.

Suggested evidence to discuss with your auditor

For A.9, these are the artefacts we suggest discussing with your auditor. The standard publishes no evidence list, so this is our reading, not a requirement.

  • A correction and corrective action protocol for each CCP
  • A worked deviation showing the hold, the evaluation and the release
  • Evidence that the cause was addressed

Where systems usually fall short

  • A correction recorded with no cause
  • A release by someone without the stated authority

How to prepare

Take the last deviation and separate the correction from the corrective action on paper. An empty second column is the gap.

Dates

Applies todayISO 22000:2018 as amended in 2024, the edition published today; certificate treatment after a new edition depends on the transition arrangements
DraftISO/DIS 22000:2026, DIS ballot closed 2026-07-29
Planning date2027-09-12 (estimate, not an ISO date)

Cross-references

8.5.4.4, 8.9.2, 8.9.3

Source

Annex A, A.9. Current edition: ISO 22000:2018. Draft: ISO/DIS 22000:2026. Retrieved 2026-10-19. The full DIS text for A.9 is sold by ISO and not held here; the sources page lists what is.